Skip to end of metadata
Go to start of metadata

The following items are expected to be completed for the project to Pass the Release Candidate Milestone.

This template must be filled out for every Release Candidate Milestone (RC0, 1, 2, x) as planned in Release Plan.

RC Release Candidate Milestone overview is available in wiki.

Practice AreaCheckpointYes/NoEvidencesNote
Product ManagementAre all tasks associated with the release been marked as "Done" in Jira?YesLink to Jira Task

 

Release ManagementAs the project team identified the reduced set of Committers who will proceed with Code Merge after RC0?Yes
  • Jinxin

 
Have all findings from previous milestones been addressed?YesLink to JIRA issueAll the high and higher are

 

DevelopmentHave all Defects of priority Highest and High been in status "Done" in Jira?YesLink to JIRA issue

 

Is there any pending commit request older than 24 hours in Gerrit?No  
Are all the Jenkins jobs successfully passed (verify + merge jobs)?Yes

Verify Jobs

Merge Jobs

 
Integration and TestingHave all CSIT Use Cases (created by each project team) passed?YesLink to evidence 
Have all end-to-end CSIT (created by Integration Team) been identified? YesLink to evidence 
Is there a Docker images available for each repository?YesLink to evidence 
Has the project code successfully passed the Daily Build process?YesLink to evidenceGoal is to ensure the latest project commit has not broken the Integration Daily Build 
Documentation

Is the team ready to contribute in the following 3 documentations:

  1. Mercury Release Notes
  2. Mercury Tarball Installation
  3. Mercury Docker Installation
Yes  
  • No labels